Lavaca-Navidad River Authority & Corpus Christi Water to Perform Scheduled Maintenance

 

City of Corpus Christi

CORPUS CHRISTI, TEXAS (News Release) - On Tuesday, September 29, the Lavaca-Navidad River Authority (LNRA), Corpus Christi Water (CCW), and their contractors will begin scheduled maintenance and upgrades to the Mary Rhodes Pipeline (MRP) pump stations.

The work includes scheduled maintenance at the Lake Texana Pump Station in Edna, Texas. At the Woodsboro and Bloomington Pump Stations, crews will install permanent backup pumps and variable frequency drives to improve efficiency and upgrade electrical systems and valve actuators.

To ensure crews can complete the work safely, pumping through the MRP will be temporarily reduced as follows:

  • September 29 and September 30 - MRP will be offline (0 MGD)

  • October 1 to October 22 - Schedule 3 Operations (55 MGD)

  • October 22 to November 16 - Schedule 2b Operations (43 MGD)

  • November 16 - Return to Schedule 4 Operations (72 MGD)

During this period, CCW will rely primarily on water supplies from the Western Reservoirs and supplement with the Nueces Groundwater Program.

 
 
South Texas Community News

Founded in 2020, STCN provides news, traffic updates, weather forecasts, investigations, notices of events and items of interest for the Coastal Bend.

https://southtexascommunitynews.com/
Previous
Previous

Two Arrested Following Narcotics Search in Jim Wells County

Next
Next

DMC Baking/Pastry Student Advances to World Food Championships