CORPUS CHRISTI – (News Release) Street closures along major City streets impacting motorists and pedestrians are listed below. These closures may be due to construction, special event activity, or maintenance. All closures are subject to change due to weather, emergency work, or other circumstances.
Work zone safety is a priority. Motorists are advised to slow down, follow posted speed limits, pay attention, watch out for workers, obey signs and flaggers, and allow additional travel time for delays.
CITY STREET RECONSTRUCTION OR MAINTENANCE PROJECTS
Brawner Parkway – Kostoryz Road to Carroll Lane (Bond 2018)
During Phase 2 of construction, Brawner Parkway (north and south of the median) will be reduced to one-way traffic flow in the eastbound direction. The following traffic changes and lane closures will be implemented:
Brawner Parkway's westbound lane (south of median) is closed for construction. The eastbound lane will remain open for use during this first phase of construction.
Brawner Parkway's westbound lane (north of median) is closed for construction. The eastbound lane will remain open for use during this first phase of construction.
Baldwin Boulevard – SH 286 (Crosstown Expressway) to Port Avenue
The contractor will implement temporary lane closures along Baldwin Boulevard from SH 286 (Crosstown Expressway) to Port Avenue.
Junior Beck Drive – Bear Lane to Old Brownsville Road (Bond 2018)
Junior Beck Drive is temporarily converted to one-way only traffic southbound from Bear Lane towards Old Brownsville Road for Phase 2 of the project. The Corporate Drive intersection at Junior Beck Drive is temporarily closed. Local access from the South Padre Island Drive (SPID) Access Road will always be maintained. Wayfinding and detour signage will be in place to guide motorists to their destinations. The temporary one-way and intersection closures are expected to last several months.
Leopard Street – Palm Drive to Nueces Bay Boulevard (Bond 2018)
Leopard Street is reduced to one lane, in each direction, along the eastbound lanes (south side) of Leopard Street between Nueces Bay Boulevard and Battlin' Buc Boulevard. The intersection at Leopard Street and Nueces Bay Boulevard is open to traffic. Additional temporary intersection closures will be implemented along the south side of Leopard Street as construction progresses.
Park Road 22 Bridge and Channel – Whitecap Boulevard to Commodores Drive (SH 361)
Park Road 22 is closed for construction on the south side (eastbound lanes) between Compass Street and Cruiser Street. Motorists traveling eastbound (south side) along Park Road 22 are shifted to the westbound lanes (north side) between Compass Street and Cruiser Street. In each direction, travel lanes are reduced to one lane between Compass Street and Cruiser Street.
Staples Street – Autotown Drive to Barracuda Place (Street Preventative Maintenance Program)
The contractor for the Public Works Department will implement temporary lane closures along Staples Street to perform street maintenance. Several major intersections along Staples Street will experience temporary closures or restrictions. Motorists should seek alternate routes to avoid construction and delays. Construction is expected to last several weeks.
Staples Street – Baldwin Boulevard to Kostoryz Road (Bond 2018)
During Phase 1 of construction on Staples Street, between Baldwin Boulevard and Kostoryz Road, drivers and pedestrians should expect the following traffic changes:
The northbound lanes and center-turn lane (east side) of Staples Street, between Baldwin Boulevard and Kostoryz Road, will be closed for construction. Traffic will be shifted to the west side of Staples Street (southbound lanes) and reduced to one lane in each direction.
Traffic along northbound Staples Street will be shifted to the west side (southbound lanes) of the roadway approaching the Kostoryz Road intersection.
The inside left-turn lane will be closed along Kostoryz Road at the Staples Street intersection.
The intersection of Texas Avenue at Staples Street, on the east side, will be temporarily closed for utility line installations.
Sidewalks within the construction zone will be closed on the east side of Staples Street.
Swantner Drive – Indiana Avenue to Texan Trail (Bond 2018)
Swantner Drive is closed to thru traffic between Ralston Street and Glazebrook Street. Chamberlain Street and Vaky Street are open for local traffic. McCall Street will remain open from Reid Drive to Swantner Drive to allow access to the Lindale Senior Center. Reid Drive, Glazebrook Street, and Swantner Drive from Glazebrook Street to Texan Trail are open.
CITY PERMITTED CLOSURES
Born Street – South Water Street to South Chaparral Street
The contractor for AEP Texas will be doing equipment maintenance along Born Street. The contractor will require a temporary full street closure of Born Street from South Water Street to South Chaparral Street to allow crews to work in the affected area. Work at this location is expected to last several days.
Carancahua Street – Agnes Street to Coopers Alley
Contractors for the city are implementing several temporary street closures to make emergency repairs on a wastewater line. Carancahua Street temporary street closure begins just north of Agnes Street intersection. Side streets leading to Carancahua Street are also temporarily closed. Other streets adjacent to the construction site may be temporally closed to extend the work zone. Residents and businesses affected by the closures will always have access to their destinations. Construction is expected to last several weeks.
Flato Road – Bates Drive and Bear Lane (IPR)
The contractor for the city is implementing a temporary street closure to clean and televise a wastewater line along Flato Road between Bates Drive and Bear Lane. Motorists traveling on Flato Road will be directed around the temporary street closure. Residential and business access will not be affected by the temporary street closure. Maintenance is expected to last 30 days.
Kostoryz Road – at Gollihar Road Intersection
The contractor for AEP Texas is performing maintenance of electrical facilities near the intersection of Kostoryz Road and Gollihar Road. The contractor will implement temporary lane closures along southbound travel lanes of Kostoryz Road approaching the Gollihar Road intersection. Work at this location is expected to last several weeks.
Kostoryz Road – at McArdle Road Intersection
The contractor for AEP Texas is performing maintenance of electrical facilities at the intersection of Kostoryz Road and McArdle Road. The contractor will implement temporary lane closures along northbound travel lanes of Kostoryz Road approaching the McArdle Road intersection. The contractor has secured police officers to assist with traffic control if traffic signals become inoperable during maintenance operations. Work at this location is expected to last several weeks.
Kostoryz Road – Holly Road to Johanna Street
The contractor for AEP Texas is performing upgrades of electrical facilities along Kostoryz Road from Holly Road to Johanna Street. The contractor will implement temporary lane closures along the northbound lanes of Kostoryz Road. Work at this location is expected to last one month.
Leopard Street – Doss Street to Peabody Avenue
The contractor for AT&T will be conducting temporary lane closures along Leopard Street from Doss Street to Peabody Avenue to complete a conduit relocation. Work at this location is expected to last several months.
McArdle Road – Ennis Joslin Drive to Nile Drive
The contractor for AEP Texas is performing electrical equipment upgrades on the north side of McArdle Road from Ennis Joslin Drive to Nile Drive. The contractor will implement temporary lane closures along McArdle Road and temporary sidewalk closures on the North side of McArdle Road. Work at this location is expected to last one month.
McKenzie Street – 18th Street to 17th Street
A residential contractor is temporarily closing the street to position a crane to assist with concrete wall construction. Temporary street closures will be implemented as needed for two months. Residents will be notified of the temporary closures, and residential access will be provided.
Mexico Street – Howard Street to Caldwell Street (Guerra Underground)
The subcontractor for Flat Iron Dragados is installing a new wastewater line between Lipan Street and Caldwell Street as part of the New Harbor Bridge Utility Relocation Project. Construction has progressed to the next section. The third phase starts at Howard Street and extends to Caldwell Street. Construction will require a temporary full street closure of Mexico Street. Traffic will be detoured where closures are needed at intersections. Residents and places of worship will always have access during construction. Construction is expected to last several months.
Molina Drive – Bloomington Street to Villarreal Drive
The residential contractor is temporarily closing the street to position a crane to assist with concrete wall construction. Temporary street closures will be implemented as needed for two months. Residents will be notified of temporary closures, and residential access will be provided.
North Carancahua Street – Buffalo Street to Antelope Street
The contractor for AEP Texas will be doing equipment maintenance along North Carancahua Street. The contractor will require a temporary full street closure of North Carancahua Street from Buffalo Street to Antelope Street to allow crews to work in the affected area. Work at this location is expected to last several days.
Ocean Drive – Ropes Street to Sinclair Street (AEP Texas)
The contractor for AEP Texas is replacing a streetlight pole assembly and will conduct daily lane closures for the left lanes in each direction of Ocean. Construction is expected to last one week.
Oso Parkway – Marseille Drive and Beauvais Drive
City Storm Water Maintenance Crews will replace drainage infrastructure at a drainage crossing underneath Oso Parkway. City crews will set up a temporary full street closure of Oso Parkway to perform maintenance repairs. Message boards and construction signage will be in place to guide motorists around the closure. Residential access will not be affected by the temporary street closure. Maintenance repairs are expected to be completed by Monday, August 8.
Paul Jones Avenue – at Sims Drive Intersection
The contractor for AEP Texas will be doing equipment maintenance at the intersection of Paul Jones Avenue and Sims Drive. Contractors are implementing daily one-lane flagger operations at the intersection to assist motorists around the work area. Work at this location is expected to last several weeks.
Port Avenue – Chaparral Street to IH-37
The City Public Works department contractor performs street maintenance on Port Avenue between Chaparral Street and IH-37 Access Road. Maintenance crews will be cleaning expansion joints and performing concrete repairs as part of the City's IDIQ project. Motorists should expect various daily lane closures throughout the project limits. Maintenance work is expected to last 30 days.
Port Avenue – Horne Road to Prescott Street (SH 286 Frontage) (Clark Pipeline)
The contractor is replacing a 16-inch water main along South Port Avenue from Horne Road to Baldwin Boulevard. The construction of the water main is divided into several phases. Construction for the next phase will affect Port Avenue from Horne Road to Tarlton Street. Southbound Port Avenue will remain reduced to one lane, utilizing the center turn lane as the travel lane. Northbound Port Avenue travel lanes will not be affected. Construction at this location is estimated to last several months.
Rodd Field Road – at Southhaven Drive Intersection
The contractor for AEP Texas is performing maintenance of electrical facilities at Rodd Field Road and Southhaven Drive intersection. Contractors are implementing daily one-lane flagger operations at the intersection to assist motorists around the work area. Work at this location is expected to last several weeks.
Tancahua Street – Leopard Street to Lipan Street (Emergency Waterline Repairs)
Tancahua Street from Leopard Street to Lipan Street is closed for emergency waterline repairs. Temporary lane closures along the existing closure may be required during the repair process.
Businesses within the affected area will have continuous driveway access. Water services will continue for all customers along the construction path. Work is expected to last one month.
Starr Street – Chaparral Street to Mesquite Street
The contractor for Spectrum is installing new cable and communication services for a downtown business. The contractor will implement temporary sidewalk and parking lane closures to create a work area to perform directional drilling operations. The closure will be set up daily and is expected to last several weeks.
Surfside Boulevard – Access Road to Surfside Park
The contractor for private development is temporarily closing the access road to Surfside Park to connect a new waterline main to an existing waterline. To continue the new waterline main construction, the contractor is also implementing a temporary full street closure on Stewart Place, between Surfside Boulevard and the dead end. Construction is expected to last one month.
South Carancahua Street – Coleman Avenue to Park Avenue
The contractor for St. James Episcopal School of Corpus Christi will be doing concrete repairs on the school’s pedestrian bridge. The contractor will implement temporary lane reductions from Coleman Avenue to Park Avenue. Construction work at this location is expected to last one month.
Villa Drive – Baldwin Boulevard to Agnes Street
The contractor for the City Utilities Department is performing emergency repairs to a wastewater manhole. Villa Drive is temporarily closed to traffic. Detours will guide motorists around the temporary street closure. Local traffic will have access from Baldwin Boulevard and Agnes Street. The temporary street closure is expected to last one month.
Wooldridge Road – Mystic Star Drive to Victoria Park Road
The contractor for AEP Texas is doing equipment maintenance along Wooldridge Road near the Victoria Park Road intersection. Contractors are implementing daily one-lane flagger operations at the intersection to assist motorists around the work area. Work at this location is expected to last several weeks.